1 |
|
Construction of new tower with pile foundation in place of river erroded tower at LOC No 371 of 132kV depota dekiajuli TL |
30-09-2024 10:00 |
21-11-2024 14:00 |
25-11-2024 16:00 |
|
|
2 |
|
Supply, erection and commissioning of battery bank and battery charger at
substations under Lower Assam Region in AEGCL |
23-10-2024 10:00 |
21-11-2024 12:00 |
22-11-2024 17:00 |
|
|
3 |
|
Procurement of 1(one) no. of 33kV Vacuum Circuit Breaker under 220kV Sarusajai GSS, AEGCL |
27-09-2024 11:00 |
21-11-2024 12:00 |
22-11-2024 15:00 |
|
|
4 |
|
Procurement of 9 nos. of industrial Air Conditioners at 132/33 kV AIIMS GSS, AEGCL. |
23-10-2024 11:00 |
21-11-2024 12:00 |
22-11-2024 14:30 |
|
|
5 |
|
Construction of flood affected tower and associated works of
transmission line at Loc. 225 A of 132 KV Nalkata Gohpur line |
14-10-2024 16:00 |
20-11-2024 14:00 |
22-11-2024 14:00 |
|
|
6 |
|
Construction of flood affected tower and associated works of
transmission line at Loc. 73 of Nalkata Dhemaji line |
14-10-2024 13:30 |
20-11-2024 14:00 |
22-11-2024 14:00 |
|
|
7 |
|
Construction of 132 KV D+0 tower (01 No) on pile foundation in
place of river eroded tower at Loc. No. 136 of 132 KV DibrugarhTinsukia line including associated works |
14-10-2024 12:00 |
20-11-2024 14:00 |
22-11-2024 14:00 |
|
|
8 |
|
Procurement of C-materials i.e. clamps, connectors and hardware fittings
etc. at 132/33 KV AIIMS GSS |
02-11-2024 11:00 |
21-11-2024 12:00 |
22-11-2024 14:00 |
|
|
9 |
|
Route Survey for construction of 220 kV DOuble Circuit transmission line from Upcoming 400/220 KV SOnapur GIS to 220 KV Substation at TATA semiconductor plant under AEGCL |
26-10-2024 12:00 |
18-11-2024 10:00 |
19-11-2024 15:30 |
|
|
10 |
|
Procurement of 132kV Isolator for 50MVA TRAFO-I & 25MVA TRAFO-II at 132kV Nalkata GSS. |
21-09-2024 13:00 |
18-11-2024 14:00 |
19-11-2024 12:00 |
|
Tender Cancelled
|
11 |
|
Construction of Main gate with security booth along with RCC Box culvert for newly constructed administrative building, Depota, AEGCL |
25-10-2024 10:00 |
16-11-2024 12:00 |
18-11-2024 13:00 |
|
|
12 |
|
Height Raising/ Shifting of 220KV Mirza-Sarusajai D/C Transmission line for elevated corridor of
Railway line near Deepor Beel area under Deposit Scheme-PACKAGE B |
21-09-2024 10:00 |
13-11-2024 12:00 |
14-11-2024 17:00 |
|
|
13 |
|
Construction of Bay equipment foundation including erection of mounting structures and necessary civil works and dismantling of existing capacitor bank for Augmentation of 31.5 MVA transformer along with associated bay equipments at 132/33kV GSS, Sankardevnagar, AEGCL. |
22-10-2024 10:00 |
12-11-2024 12:00 |
14-11-2024 13:00 |
|
|
14 |
|
1) Repairing and renovation of RCC Type-V Quarter unit-A at Baghjap AEGCL campus.
2) Repairing and renovation of RCC Type-V Quarter unit-B at Baghjap AEGCL campus.
3) Repairing and renovation of RCC Type-V Quarter unit-C at Baghjap AEGCL campus.
4) Repairing and renovation of RCC Type-V Quarter unit-D at Baghjap AEGCL campus.
5) Repairing and renovation of RCC Type-VI Quarter unit-B at Baghjap AEGCL campus.
6) Repairing and renovation of RCC Type-IV Quarter unit-B at Baghjap AEGCL campus
7) Construction of security barrack (Type-IV) along with washroom at Baghjap AEGCL campus
8) Construction of 2 nos. of RCC septic tank (of 10 users), soak pit at Baghjap AEGCL campus
9) Construction of a washroom for quarter (Type-VI) at Baghjap AEGCL campus |
23-10-2024 11:00 |
12-11-2024 12:00 |
13-11-2024 14:00 |
|
|
15 |
|
Construction of Transformer Pad and Fire Protection wall for Augmentation of 31.5 MVA transformer along with associated bay equipments at 132/33kV GSS, Sankardevnagar, AEGCL. |
18-10-2024 10:00 |
08-11-2024 12:00 |
12-11-2024 13:00 |
|
|
16 |
|
Supply, Erection, Testing and commissioning of 1 no. of 33kV Vacuum Circuit Breaker for 33kV Baskandi Feeder at 132kV Pailapool GSS |
01-10-2024 12:00 |
11-11-2024 14:00 |
12-11-2024 11:30 |
|
|
17 |
|
Supply of 1 no set 33kV vacuum circuit breaker to kept as spare at 132kV haflong GSS |
01-10-2024 12:00 |
11-11-2024 14:00 |
12-11-2024 11:30 |
|
|
18 |
|
Additional civil works at 132/33kV GSS, Diphu, AEGCL due to the extension of 132kV Transfer Bus
for future provision of another 132kV Bay at 132kV GSS, AEGCL, Diphu |
18-10-2024 12:00 |
08-11-2024 12:00 |
11-11-2024 14:30 |
|
|
19 |
|
Repairing work of towers of 132kV Dhaligaon-Barnagar S/C Transmission Line, AEGCL. |
25-09-2024 12:00 |
09-11-2024 14:00 |
11-11-2024 12:00 |
|
|
20 |
|
Leg repairing, mufflering & earthing of towers of 132kV Dhaligaon-Nalbari Transmission Line, AEGCL. |
25-09-2024 12:00 |
09-11-2024 14:00 |
11-11-2024 12:00 |
|
|
21 |
|
33kV Bypass bus extension for 3 Nos. of 33kV bays & erection of 1 No. Jack bus for 33kV Railway feeder bay at 132kV
Dhaligaon GSS, AEGCL. |
25-09-2024 12:00 |
09-11-2024 14:00 |
11-11-2024 12:00 |
|
|
22 |
|
Leg repairing & mufflering works of towers of:
(a) 220kV BTPS-Agia D/C transmission line, AEGCL
(b) 132kV Dhaligaon-Gossaigaon S/C transmission line, AEGCL. |
25-09-2024 12:00 |
09-11-2024 14:00 |
11-11-2024 12:00 |
|
|
23 |
|
Painting of control room cum office building at 132 KV GSS, AEGCL, Moran |
24-10-2024 12:00 |
06-11-2024 12:00 |
06-11-2024 15:00 |
|
|
24 |
|
For repairing of fire safety equipments/accessories of Bijulee Bhawan |
16-10-2024 11:30 |
02-11-2024 15:00 |
04-11-2024 14:00 |
|
|
25 |
|
Supply, dismantling, construction, erection and commissioning of 2 Nos 220 kV Bays at 400/220 kV Misa S/s (POWERGRID) and associated works etc. |
02-09-2024 12:00 |
28-10-2024 12:00 |
29-10-2024 14:00 |
|
|
26 |
|
SUPPLY OF 48V, 250AH VRLA BATTERY BANK
AT 132 KV PANCHGRAM GSS |
07-10-2024 12:00 |
28-10-2024 14:00 |
29-10-2024 11:30 |
|
|
27 |
|
ERECTION OF TOWER BY DISMANTLING THE EXISTING TOWER LOCATION NO 37 OF
132kV LILO BALIPARA-SONABIL D/C LINE WITH CONSTRUCTION OF NEW FOUNDATION
ALONG WITH STRINGING OF CONDUCTOR FROM LOC. NO. 34 TO 38 |
10-09-2024 10:00 |
22-10-2024 12:00 |
25-10-2024 13:00 |
|
|
28 |
|
Water proofing treatment by concreting at 400kV Kukurmara GSS Control Room Building |
04-10-2024 16:00 |
25-10-2024 12:00 |
25-10-2024 13:00 |
|
|
29 |
|
Construction of RCCslow sand filter 24kL capacity at 132kv Srikona GSS under Shilchar T T Division |
30-09-2024 12:00 |
21-10-2024 14:00 |
22-10-2024 11:30 |
|
|
30 |
|
Height Raising/ Shifting of 220KV Mirza-Sarusajai D/C Transmission line for elevated corridor of
Railway line near Deepor Beel area under Deposit Scheme-PACKAGE A |
16-09-2024 18:00 |
18-10-2024 12:00 |
19-10-2024 17:00 |
|
|
31 |
|
“Installation of Aluminium partition from the existing one upto the height of ceiling along with installation of an split type Air conditioning system at the Chamber of Medical officer, ground floor, west side, Bijulee Bhawan”. |
13-09-2024 14:00 |
18-10-2024 12:00 |
19-10-2024 14:00 |
|
|
32 |
|
Repairing and renovation of main gate to RCC hostel at 400kV Kukurmara GSS, AEGCL |
04-10-2024 12:00 |
19-10-2024 11:00 |
19-10-2024 12:00 |
|
|
33 |
|
Height Raising/ Shifting of 220KV Mirza-Sarusajai D/C Transmission line for elevated corridor of
Railway line near Deepor Beel area under Deposit Scheme-PACKAGE B |
21-09-2024 10:00 |
15-10-2024 12:00 |
18-10-2024 17:00 |
|
|
34 |
|
“Preparation of Master Plan of 1 no. of 33/220 kV Generating Substation for evacuation of power from 22.5MW
Karbi Langpi Middle I and 24MW Karbi Langpi Middie II” |
29-08-2024 10:00 |
16-10-2024 10:00 |
18-10-2024 15:00 |
|
|
35 |
|
Emergency repairing of damaged tower at Loc-48, Loc-60 and Loc-61 of 132kV Capital-Narengi-CTPS-Sonapur DC Transmission Line, AEGCL. |
28-08-2024 11:00 |
15-10-2024 12:00 |
18-10-2024 14:30 |
|
|
36 |
|
Temporary re-arrangement for ensuring power flow through 132kV Kahilipara-Rangia Transmission Lines
against height raising works for the new 6-lane highway of APWD at North Guwahati. |
09-09-2024 16:00 |
18-10-2024 12:00 |
18-10-2024 14:30 |
|
|
37 |
|
“Replacement of existing Ground Wire with 24F Overhead OPGW from
132KV Kahilipara GSS to 132KV Dispur GSS and Commissioning of DTPC
between 132KV Kahilipara and 132KV Dispur |
20-09-2024 12:00 |
14-10-2024 17:00 |
15-10-2024 14:00 |
|
|
38 |
|
Supply of ACSR Panther, ACSR Zebra and ACSR Moose Conductors in Lower Assam, Central Assam and Upper Assam Region of AEGCL |
21-08-2024 14:00 |
08-10-2024 14:00 |
09-10-2024 14:00 |
|
|
39 |
|
Procurement along with Installation of 14 Nos. of
Air Conditioners for Control Rooms, Battery Room
& Charger Room at various GSS under Silchar T&T
Division, AEGCL, Silchar |
16-09-2024 12:00 |
07-10-2024 14:00 |
08-10-2024 11:30 |
|
|
40 |
|
Procurement of Automatic Transformer Oil BDV
Testing kit with Stainless Steel Oil sampling bottle
(1 Litre capacity) & Syringe for Oil sampling against
Dullavcherra GSS |
16-09-2024 11:00 |
07-10-2024 14:00 |
08-10-2024 11:30 |
|
|
41 |
|
Cleaning and repairing of Staffs Colony’s overhead steel tank & RCC slow sand filter along with necessary Connection of pipelines from Colony’s Overhead water tank to Control room water tank at 132kV Depota GSS, AEGCL |
29-08-2024 12:00 |
03-10-2024 11:00 |
04-10-2024 13:00 |
|
|
42 |
|
Procurement and installation of ACs at 132/33kV Dhekiajuli GSS |
19-08-2024 11:00 |
03-10-2024 11:00 |
03-10-2024 12:00 |
|
|
43 |
|
Procurement of fixed and moving contact spare of 33kV Isolator (Twist and Turn type) for maintenance work at 132/33kV Kahilipara GSS. |
14-08-2024 11:00 |
30-09-2024 12:00 |
01-10-2024 14:30 |
|
|
44 |
|
Height Raising /Shifting of 132KV D/C Gauripur-Bilashipara Transmission line & 132KV S/C GossaigaonGauripur Transmission Line |
28-08-2024 12:00 |
25-09-2024 12:00 |
26-09-2024 16:00 |
|
|
45 |
|
Procurement of furniture at Transit Camp, Officer's Hostel, Security and Staffs Quarters at 132 KV AIIMS GSS |
06-09-2024 11:00 |
24-09-2024 12:00 |
25-09-2024 15:00 |
|
Tender Cancelled
|
46 |
|
Augmentation works of 132kV Main Bus Strengthening at 132 KV Nalkata GSS, AEGCL |
25-07-2024 12:00 |
18-09-2024 12:00 |
20-09-2024 14:00 |
|
|
47 |
|
Supply of 220KV Potential Transformers for Upper Assam Region of AEGCL |
30-08-2024 12:00 |
19-09-2024 12:00 |
20-09-2024 14:00 |
|
|
48 |
|
Extension and repairing of old quarter which is being temporarily used as RE office at 132kV APM GSS, AEGCL,Jogighopa. |
30-08-2024 14:00 |
19-09-2024 12:00 |
19-09-2024 13:00 |
|
|
49 |
|
SUPPLY OF 1 (ONE) NO. OF TRANSFORMER WINDING
RESISTANCE METER KIT FOR T&C DIVISION, AEGCL, NORTH
LAKHIMPUR |
05-08-2024 12:00 |
10-09-2024 12:00 |
11-09-2024 12:00 |
|
|
50 |
|
SUPPLY OF 1 (ONE) NO. OF FULLY AUTOMATIC TRANSFORMER
OIL TAN DELTA AND RESISTIVITY TEST KIT FOR MRT DIVISION,
AEGCL, JORHAT |
05-08-2024 12:00 |
09-09-2024 12:00 |
10-09-2024 12:00 |
|
|