1 |
|
Construction of First Floor of Existing Transit Camp Building at 132/33 KV GSS, AIIMS, Changsari |
30-12-2023 12:00 |
19-01-2024 12:00 |
22-01-2024 16:00 |
|
|
2 |
|
Supply of furniture for Kahilipara community Hall at Kahilipara AEGCL Colony. |
20-12-2023 11:00 |
20-01-2024 12:00 |
22-01-2024 14:30 |
|
|
3 |
|
Construction of boundary wall at 132kV AIIMS GSS under Deposit Scheme |
30-12-2023 12:00 |
19-01-2024 12:00 |
20-01-2024 16:00 |
|
|
4 |
|
1)Extra earth filling work at 132/33kV AIIMS GSS.
2)Extra water works (Piping and pump house) for colony area at 132/33kV AIIMS GSS.
3)Installation of deep tube well in colony area at 132/33kV AIIMS GSS. |
01-01-2024 11:00 |
19-01-2024 12:00 |
20-01-2024 14:00 |
|
|
5 |
|
Procurement of spare equipment for 132/33kV AIIMS GSS, AEGCL at Changsari, Guwahati” |
28-12-2023 12:00 |
17-01-2024 12:00 |
19-01-2024 15:00 |
|
|
6 |
|
Short tender for Supply, installation, configuration and
successful implementation of Active Directory services to
provide centralized domain control functionality for
AEGCL along with all associated accessories and post
installation support for 3 years at AEGCL. |
09-01-2024 17:00 |
18-01-2024 12:00 |
18-01-2024 18:00 |
|
|
7 |
|
Fabrication & Installation of a new gate at SLDC, AEGCL, Kahilipara, Ghy-19 |
26-12-2023 12:00 |
17-01-2024 12:00 |
18-01-2024 12:00 |
|
|
8 |
|
Earthing of 7 nos. of towers of 400kV LILO line under 400kV Kukurmara GSS,AEGCL |
04-01-2024 10:00 |
18-01-2024 11:00 |
18-01-2024 12:00 |
|
|
9 |
|
Supply, Installation and Commissioning o f dedicated 4 Mbps Internet Leased Line(ILL) connectivity with SLA agreement at various locations of Assam Electricity Grid Corporation Limited under “Scheme for Special Assistance to State for Capital Investment for FY 2023- 24 |
10-01-2024 10:00 |
17-01-2024 10:00 |
17-01-2024 16:30 |
|
|
10 |
|
Improvement of space (upto the length where oil barrels are kept) with
construction of Paver Block along with associated works at the southern
side of Bijulee Bhawan, Paltanbazar, Ghy-01”. |
01-01-2024 14:00 |
17-01-2024 12:00 |
17-01-2024 13:00 |
|
|
11 |
|
Construction of approach road towards Transit Camp with PCC (upto
the existing approach road of 132/33 KV Paltanbazar GIS) along with
PCC at two wheeler parking Shed & installation of street lights at
Bijulee Bhawan Premises”. |
01-01-2024 14:00 |
17-01-2024 12:00 |
17-01-2024 13:00 |
|
|
12 |
|
Short tender for Supply, installation, configuration and
successful implementation of Desktops along with all
associated accessories and post installation support for 3
years at Assam Electricity Grid Corporation Limited
Offices. |
09-01-2024 17:00 |
12-01-2024 10:00 |
12-01-2024 17:00 |
|
|
13 |
|
Geotechnical Investigation for construction of 1 nos. of 220/132/33 kV GIS Grid Substation at Morigaon under AEGCL |
01-01-2024 10:00 |
11-01-2024 12:00 |
12-01-2024 12:00 |
|
|
14 |
|
Repairing of Assam Type office of the AGM,Goalpara T&T Division,Agia,AEGCL |
04-01-2024 10:00 |
11-01-2024 10:00 |
11-01-2024 11:00 |
|
|
15 |
|
1) Repairing of Assam type quarters and construction of bathrooms at AEGCL colony at
220kV Sarusajai GSS.
2) Construction of drain in front of store room at 220kV Sarusajai GSS campus. |
21-12-2023 11:00 |
09-01-2024 12:00 |
10-01-2024 14:30 |
|
|
16 |
|
1) Repairing and renovation of Quarter No. T/III/03/1/SF-1 at Sarusajai GSS Campus
2) Repairing and renovation of Quarter No. T/III/03/1/SF-2 at Sarusajai GSS Campus
3) Repairing and renovation of Quarter No. T/IV/04/1/FF-1 at Sarusajai GSS Campus
4) Repairing and renovation of Quarter No. T/IV/04/1/FF-2 at Sarusajai GSS Campus
5) Repairing and renovation of Quarter No. T/IV/04/1/FF-3 at Sarusajai GSS Campus
6) Repairing and renovation of Quarter No. T/IV/04/1/GF-2 at Sarusajai GSS Campus |
21-12-2023 11:00 |
09-01-2024 12:00 |
10-01-2024 14:00 |
|
|
17 |
|
Providing chain link fencing and gate for the Kahilipara Community Hall at Kahilipara AEGCL Colony |
20-12-2023 11:00 |
08-01-2024 12:00 |
09-01-2024 15:30 |
|
|
18 |
|
Construction of bituminous road after scarifying existing bituminous road for the east side road from the main access road of AEGCL Kahilipara colony. |
20-12-2023 12:00 |
08-01-2024 12:00 |
09-01-2024 14:00 |
|
|
19 |
|
Development, Installation, Customization & Deployment of advance firewalls having next generation features in all offices and GSS with modernization of WAN interconnectivity of AEGCL |
30-12-2023 18:00 |
08-01-2024 14:00 |
09-01-2024 14:00 |
|
|
20 |
|
1. Supply of children’s park items for Kahilipara community Hall at Kahilipara AEGCL colony. |
20-12-2023 11:00 |
05-01-2024 12:00 |
06-01-2024 14:00 |
|
|
21 |
|
Preparation of Master Plan & Route Survey for Construction of 1 no. 132/33 kV Grid Substation at Dhupdhara (Khutabari Part-V) along with the associated transmission lines under AEGCL(under AIIB Phase-II funding) |
29-12-2023 11:00 |
05-01-2024 15:00 |
06-01-2024 12:00 |
|
|
22 |
|
Turnkey Construction of a 132kV Railway Traction Bay at 132kV Bordubi GSS, AEGCL including
Supply of Bay Equipment and line bay materials and associated works etc |
12-12-2023 12:00 |
02-01-2024 12:00 |
04-01-2024 14:00 |
|
|
23 |
|
1. Procurement of 18 Nos. of 33kV LA s for sub-stations under T&T Division , AEGCL, North Lakhimpur. |
02-12-2023 12:00 |
02-01-2024 12:00 |
02-01-2024 15:00 |
|
|
24 |
|
Civil Works for Construction of 33 kV Dedicated feeder bay at 132 kV Sishugram GSS AEGCL North Guwahati for JICA Water Supply Project |
13-12-2023 12:00 |
30-12-2023 12:00 |
02-01-2024 14:00 |
|
|
25 |
|
Construction of Server Room in Bijulee Bhawan, AEGCL, Paltanbazar,
Guwahati-01 |
15-12-2023 14:00 |
29-12-2023 14:00 |
30-12-2023 15:00 |
|
|
26 |
|
1. Civil works at MRT TRW Sub- Division, at Kahilipara, AEGCL.
.
2. Painting and minor repairing works at MRT TRW Sub- Division, at Kahilipara
AEGCL.
3. Construction of watershed staging for water tank at O/o the DGM, LA T&C and
Comm. Circle, AEGCL, Narengi, Ghy-26. |
14-12-2023 10:00 |
29-12-2023 17:00 |
30-12-2023 12:00 |
|
|
27 |
|
Construction of 3 (three) Nos. of new tower with pile foundation in place of river eroded tower at Loc- 451, 452 and 453 of 220 KV D/C Rangia-Salakati Line |
02-12-2023 18:00 |
26-12-2023 12:00 |
28-12-2023 14:00 |
|
|
28 |
|
1. Construction of slow sand water filter and reservoir at 132kV GSS, AEGCL,
Demaji |
01-12-2023 12:00 |
26-12-2023 14:00 |
28-12-2023 12:00 |
|
|
29 |
|
1. Construction of a store building at 220KV GSS, AEGCL, Namrup.
2. Construction of RCC Culvert(3 nos.) over cable trenches of approach road crossing &
installation of RCC pipe culvert (1 No.) in the approach road at 220KV GSS, AEGCL,
Namrup |
04-12-2023 12:00 |
26-12-2023 12:00 |
26-12-2023 15:00 |
|
|
30 |
|
1. Renovation/ repairing of Type III residential quarter at 132kV GSS,
AEGCL, Nazira (Quarter no: 5),
2. Construction of RCC slow sand filter (24kL) at 132kV GSS, AEGCL,
LTPS,
3. Installation of Deep Tube Well for Control room building at 132/33kV
GSS, AEGCL, LTPS,
4. Repairing/ renovation of the Officer’s Hostel at 132kV GSS, AEGCL,
Betbari,
5. Repairing and painting of the Officer’s Hostel at 132lv GSS, AEGCL,
Betbari,
6. Renovation of 2(two) nos. of Type V quarter at 132kv GSS, AEGCL,
Nazira |
04-12-2023 12:00 |
24-12-2023 12:00 |
26-12-2023 14:30 |
|
|
31 |
|
Turnkey construction of 33kV Feeder Bay along with associated works at 132kV Narengi GSS for power supply to OIL |
15-11-2023 12:00 |
19-12-2023 12:00 |
21-12-2023 14:00 |
|
|
32 |
|
Height raising of 220kV Samaguri-Sarusajai D/C transmission line between span Loc no.78(T)
to Loc no. 87(T). |
01-11-2023 11:00 |
18-12-2023 12:00 |
19-12-2023 15:00 |
|
|
33 |
|
Height raising of 220kV Samaguri-Sarusajai D/C transmission line between span Loc no. 87 to Loc no. 98. |
01-11-2023 11:00 |
18-12-2023 12:00 |
19-12-2023 14:30 |
|
|
34 |
|
1.Renovation of 2(Two) Nos. of IB rooms intended to be used as IB guest room at 132kV GSS, AEGCL, Majuli.
2.Repairing of Type-IV (B) quarter at 132kV GSS, AEGCL, Dhemaji.
3.Construction of septic tanks for Type-V quarter at 132kV GSS, AEGCL, Nalkata.
4.Repairing of 4(Four) Nos. of Staff Hostel rooms at 132kV GSS, AEGCL, Pavoi.
5.Construction of Security Barrack at 132kV GSS, AEGCL, Pavoi. |
22-11-2023 12:00 |
11-12-2023 14:00 |
13-12-2023 12:00 |
|
|
35 |
|
Package A: Restringing of conductor at 220kV D/C Samaguri-Sarusajai TL between span no. 48 to 54.
Package B: Restringing of conductor at 220kV D/C Langpi-Sarusajai TL between span no. 256 to 263. |
16-10-2023 11:00 |
11-12-2023 12:00 |
12-12-2023 14:00 |
|
|
36 |
|
Development, Installation, Customization & Deployment of Security Infrastructure along with NGFW in all offices and GSS with modernization of WAN interconnectivity of AEGCL. |
01-12-2023 10:00 |
05-12-2023 17:00 |
08-12-2023 15:00 |
|
Tender Cancelled
|
37 |
|
Renovation and Repairing of 4Nos Type-IV, 4 Nos Type-V and 2 Nos Type-VI Quarter at Samaguri GSS, AEGCL |
15-11-2023 14:00 |
06-12-2023 14:00 |
08-12-2023 15:00 |
|
|
38 |
|
Geotechnical Investigation for construction of 1 nos. of 132/33 kV Grid Substation at
Missamari under AEGCL |
09-10-2023 12:00 |
01-12-2023 12:00 |
04-12-2023 16:00 |
|
|
39 |
|
EOI FOR APPOINTMENT OF TAX CONSULTANTS OF AEGCL FROM FINANCIAL YEAR 2009-2010 TO 2021-22. |
20-11-2023 11:00 |
04-12-2023 11:00 |
04-12-2023 13:00 |
|
Tender Cancelled
|
40 |
|
Repairing of Record Room along with installation of High Almirah for Keeping files & documents at First floor,Bijulee Bhawan,Paltanbazar,Guwahati-01 |
21-11-2023 14:00 |
04-12-2023 12:00 |
04-12-2023 13:00 |
|
|
41 |
|
Supply, Installation and Commissioning of 1:1 dedicated 300MBps lease line internet connectivity with SLA agreement at Corporate Office of Assam Electricity Grid Corporation Limited, 1st Floor, Bijulee Bhawan, Paltan Bazar, Guwahati-01 under “Scheme for Special Assistance to State for Capital Investment for FY 2023-24”. |
08-11-2023 11:00 |
28-11-2023 16:00 |
29-11-2023 15:00 |
|
|
42 |
|
Earthing of 7 nos. of towers of 400kV LILO line under 400kV Kukurmara GSS,AEGCL |
10-10-2023 16:00 |
21-11-2023 12:00 |
21-11-2023 13:00 |
|
|
43 |
|
Second circuit stringing (Hotline) of Nazira-Garmur line along with construction of two nos. of 132 kV Line Bays at 132 kV Nazira GSS and 132kV Garmur GSS(Turnkey) |
12-10-2023 09:00 |
17-11-2023 12:00 |
20-11-2023 16:00 |
|
|
44 |
|
Supply of SF6 gas at substations under Mirza T&T Circle,AEGCL |
26-10-2023 16:00 |
20-11-2023 11:00 |
20-11-2023 12:00 |
|
|
45 |
|
1. Renovation of Guest House at 220KV GSS, AEGCL, Mariani
2. Repairing of 2(Two) Nos. of Type-III Quarter (Qtr. No.: 2 & 3)
at 220KV Colony, AEGCL, Mariani
3. Repairing of 2(Two) Nos. of Type-IV Quarter (Qtr. No.: 1 & 2)
at 220KV Colony, AEGCL, Mariani
4. Repairing of 1(One) No. of Type-V Quarter (Qtr. No.:3) at
220KV Colony, AEGCL, Mariani
5. Supply and Installation of submersible pump (1 No. 3HP & 1
No. 5HP) along with main pipe & development of tube wells at
132KV GSS, AEGCL, Garmur |
16-10-2023 12:00 |
15-11-2023 12:00 |
17-11-2023 14:30 |
|
|
46 |
|
1. Construction of boundary wall of the colony at 132kV GSS, AEGCL, Gohpur.
2. Laying of water supply pipeline at 132kV GSS, AEGCL, Gohpur.
3. Construction of Iron Gate at the colony entrance at 132kV GSS, AEGCL, Gohpur.
4. Construction of 7(Seven) Nos. of Septic Tanks for Type-II. IV &V Quarters at 132kV GSS, AEGCL, Gohpur |
10-10-2023 12:00 |
14-11-2023 14:00 |
16-11-2023 12:00 |
|
|
47 |
|
1. Replacement of water supply service pipeline with new pipes (CPVC) alongwith some bibcock at ASEB Colony, Kahilipara, Ghy-19
2. Construction of 9 No.s of staging along with supplying, fitting & fixing of 34 No.s of HDPE Over-head water tank for Assam Type Quarter (Type-V & VI) at ASEB Colony, Kahilipara, Guwahati-19 |
25-10-2023 14:00 |
07-11-2023 14:00 |
08-11-2023 15:00 |
|
|
48 |
|
1. Repairing, maintenance & construction of Type-III quarter at
132KV GSS, AEGCL, Dibrugarh colony used as office building
of DGM, T&T Circle, AEGCL, Dibrugarh
2. Construction of security booth at the main entrance of gate
(approach road to colony & GSS) of 132KV GSS, AEGCL,
Behiating |
09-10-2023 12:00 |
07-11-2023 12:00 |
08-11-2023 14:00 |
|
|
49 |
|
1. Construction of septic tank and associated works of IB 132kV GSS, AEGCL, Dhemaji.
2. Renovation of 2(Two) Nos. of IB rooms intended to be used as IB guest room at 132kV GSS, AEGCL, Majuli.
3. Repairing of Type-IV (B) quarter at 132kV GSS, AEGCL, Dhemaji.
4. Construction of septic tanks for Type-V quarter at 132kV GSS, AEGCL, Nalkata.
5. Repairing of 4(Four) Nos. of Staff Hostel rooms at 132kV GSS, AEGCL, Pavoi.
6. Construction of Security Barrack at 132kV GSS, AEGCL, Pavoi. |
18-10-2023 12:00 |
07-11-2023 14:00 |
08-11-2023 12:00 |
|
Tender Cancelled
|
50 |
|
1. Repairing and maintenance of existing approach road from main road to RE office with Pavers block
pavement at 132KV GSS, AEGCL, Behiating
2. Construction of RCC slow sand filter at 132KV GSS, AEGCL, Behiating
3. Construction of security barrack in place of existing temporary shed at 132KV GSS, AEGCL, Dibrugarh |
05-10-2023 12:00 |
06-11-2023 12:00 |
07-11-2023 14:00 |
|
|