1 |
|
Renovation of AEGCL Guest house at 132 kV GSS, AEGCL, Gauripur |
26-05-2022 12:00 |
15-06-2022 14:00 |
17-06-2022 14:30 |
|
Tender Cancelled
|
2 |
|
SUPPLY OF THERMOVISION CAMERA FOR TRANSMISSION LINE AND SUBSTATION OF AEGCL |
18-05-2022 09:00 |
09-06-2022 17:00 |
10-06-2022 15:00 |
|
|
3 |
|
Name of work: Procurement, Erection, Testing and commissioning of one(1) no. of 220kV DC 400AH Battery Bank with Charger for 220kV Samaguri GSS, AEGCL |
19-05-2022 11:00 |
09-06-2022 12:00 |
10-06-2022 12:00 |
|
|
4 |
|
Name of work: Renovation & repairing of IB at 132 KV Rowta GSS, AEGCL. |
19-05-2022 12:00 |
09-06-2022 12:00 |
10-06-2022 12:00 |
|
|
5 |
|
Supply of 33KV Lightning Arrester under Depota Division, AEGCL |
24-05-2022 11:00 |
07-06-2022 11:00 |
07-06-2022 12:00 |
|
Tender Cancelled
|
6 |
|
Supply of 33KV Lightning Arrester under Nagaon Division |
24-05-2022 11:00 |
07-06-2022 11:00 |
07-06-2022 12:00 |
|
Tender Cancelled
|
7 |
|
Expression of Interest for Empanelment of Advertising Agency for AEGCL. |
18-05-2022 14:00 |
02-06-2022 14:00 |
02-06-2022 15:00 |
|
|
8 |
|
Permanent protection work to protect the tower foundation by construction of new foundation with Ring Well Casing including Dismantling and erection of tower at Loc. No 332 of the 132KV Depota-Rowta line and associated works. |
05-05-2022 12:00 |
02-06-2022 11:00 |
02-06-2022 12:00 |
|
|
9 |
|
Turnkey Construction of 132kV N.F. Railway Traction Bay at 132kV Dhemaji GSS, AEGCL including Supply of Bay Equipment and line bay materials and associated works etc. |
11-05-2022 12:00 |
31-05-2022 14:00 |
01-06-2022 14:00 |
|
|
10 |
|
Turnkey Construction of 132kV N.F. Railway Traction Bay at 132kV Nalkata GSS, AEGCL including Supply of Bay Equipment and line bay materials and associated works etc. |
11-05-2022 12:00 |
31-05-2022 14:00 |
01-06-2022 14:00 |
|
|
11 |
|
Turnkey Construction of 132kV N.F. Railway Traction Bay and a Bus Coupler bay at 132kV Sonabil GSS, AEGCL including Supply of Bay Equipment and line bay materials and associated works etc. |
11-05-2022 12:00 |
31-05-2022 14:00 |
01-06-2022 14:00 |
|
|
12 |
|
Turnkey Construction of a 132kV N.F. Railway Traction Bay and a Bus PT Nay at 132kV Rowta GSS, AEGCL including Supply of Bay Equipment and line bay materials and associated works etc. |
10-05-2022 12:00 |
30-05-2022 14:00 |
31-05-2022 14:00 |
|
|
13 |
|
Empanelment at AEGCL for a period of one year with provision to extend by another one year to carry out various types of O&M works at Sub-Stations of AEGCL under Tezpur T&T Circle |
27-04-2022 10:00 |
27-05-2022 12:00 |
28-05-2022 11:00 |
|
|
14 |
|
Empanelment at AEGCL for a period of One year with provision to extend by another one year to carry out various types of O&M works related to Sub-Stations, transmission lines, OPGW related
works & Civil Works (Sub-stations & Transmissions lines) of AEGCL under T&T Circle, AEGCL, North Lakhimpur. |
26-04-2022 12:00 |
23-05-2022 14:00 |
24-05-2022 13:00 |
|
|
15 |
|
Empanelment at AEGCL for a period of one year with provision to extend by another one year to carry out various types of O&M works at Sub-Stations of AEGCL under T&T Circle, Dibrugarh |
23-04-2022 12:00 |
16-05-2022 14:00 |
17-05-2022 14:00 |
|
|
16 |
|
Empanelment at AEGCL for a period of one year with provision to extend by another one year to carry out various types of O&M works at Sub-Stations of AEGCL under |
21-04-2022 12:00 |
11-05-2022 14:00 |
12-05-2022 15:00 |
|
|
17 |
|
NON-COMPREHENSIVE ANNUAL MAINTENANCE CONTRACT FOR IT ITEMS OF AEGCL HQ, BIJULEE BHAWAN |
06-05-2022 10:00 |
12-05-2022 14:00 |
12-05-2022 15:00 |
|
|
18 |
|
Empanelment at AEGCL for a period of One year with provision to extend by another
one year to carry out various types of O&M works related to Sub-Stations,
transmission lines, OPGW related works & Civil Works (Sub-stations & Transmissions
lines) of AEGCL under Silchar T&T Circle |
26-04-2022 10:00 |
10-05-2022 14:00 |
11-05-2022 11:30 |
|
|
19 |
|
Empanelment at AEGCL for a period of one year with provision to extend by another one year to carry out various types of O&M works at Sub-Stations of AEGCL under Lower Assam T&T Circle |
13-04-2022 10:00 |
06-05-2022 14:00 |
07-05-2022 14:00 |
|
|
20 |
|
EOI for Empanelment at AEGCL for a period of one year with provision to extend by another one year to carry out various types of O&M works at Sub-Stations of AEGCL under Mirza T&T Circle |
13-04-2022 14:00 |
05-05-2022 14:00 |
06-05-2022 14:00 |
|
|
21 |
|
EOI for Empanelment at AEGCL for a period of one year
with provision to extend by another one year to carry out
various types of O&M works at Sub-Stations of AEGCL
under |
20-04-2022 10:00 |
05-05-2022 14:00 |
06-05-2022 14:00 |
|
|
22 |
|
Supply of 33KV Surge Arrestors under Nagaon T&T Division, AEGCL |
26-03-2022 10:00 |
27-04-2022 12:00 |
27-04-2022 13:00 |
|
Tender Cancelled
|
23 |
|
Supply of 33KV Surge Arrestors under Depota Division |
26-03-2022 10:00 |
27-04-2022 12:00 |
27-04-2022 13:00 |
|
Tender Cancelled
|
24 |
|
Construction of Truck Shed for newly allotted 6KLPH truck mounted Transformer Oil filtration machine at O/o the AGM, MRT Division, AEGCL, Jorhat. |
06-04-2022 12:00 |
26-04-2022 12:00 |
26-04-2022 14:00 |
|
|
25 |
|
Procurement of HF Coaxial cable(75 ohm) for Lower Assam Communication Division,AEGCL,Kahilipara |
07-04-2022 10:00 |
21-04-2022 14:00 |
21-04-2022 16:00 |
|
|
26 |
|
Procurement of Fiber to 4E1 PDH Converter for Lower Assam Communication Division
AEGCL, Kahilipara |
07-04-2022 10:00 |
21-04-2022 14:00 |
21-04-2022 16:00 |
|
|
27 |
|
Procurement of 48 V DC-DC Converter for Lower Assam Communication Division AEGCL,
Kahilipara |
07-04-2022 10:00 |
21-04-2022 14:00 |
21-04-2022 16:00 |
|
|
28 |
|
Supply of Control and Relay Panel for integration to existing system along with Energy meter and all the accessories and mandatory spares related to CRP for construction of 33kV feeder bay at Barpeta Cancer Hospital at 132/33kV Barpeta GSS. |
07-04-2022 15:00 |
13-04-2022 14:00 |
13-04-2022 15:30 |
|
|
29 |
|
Supply of earthing equipment, control & power cable and insulator strings, clamps & connectors including supply of switchyard structure and AC Marshalling KIOSK for 33kV feeder bay of Barpeta Cancer Hospital132/33kV Barpeta GSS. |
07-04-2022 15:00 |
13-04-2022 14:00 |
13-04-2022 15:30 |
|
|
30 |
|
Supply of Mandatory spares of bay equipments for 33kV feeder bay at Barpeta cancer Hospital at 132/33kV Barpeta GSS. |
07-04-2022 15:00 |
13-04-2022 14:00 |
13-04-2022 15:30 |
|
|
31 |
|
Erection works along with foundation construction and supply of all foundation materials and structure earthing including testing and commissioning related to construction of 33kV feeder bay at Barpeta Cancer Hospital at 132/33kV Barpeta GSS. |
07-04-2022 15:00 |
13-04-2022 14:00 |
13-04-2022 15:30 |
|
|
32 |
|
Supply of 33kV bay equipments alongwith their mounting structures, ACSR Panther conductor and LED Lights incl. fittings for construction of 33kV feeder bay at Barpeta cancer Hospital. at 132/33kV Barpeta GSS. |
07-04-2022 15:00 |
13-04-2022 14:00 |
13-04-2022 15:00 |
|
|
33 |
|
AUGMENTATION OF 33KV BUS
BUS-II AT NAZIRA GSS |
16-03-2022 12:00 |
12-04-2022 12:00 |
13-04-2022 14:30 |
|
|
34 |
|
Augmentation of 33kV Bus-III at Nazira GSS |
16-03-2022 12:00 |
12-04-2022 12:00 |
13-04-2022 14:30 |
|
|
35 |
|
Procurement of ACSR Zebra Conductor |
04-03-2022 12:00 |
12-04-2022 14:00 |
12-04-2022 14:30 |
|
|
36 |
|
Permanent protection work to protect the tower foundation by construction of new foundation with Ring Well Casing including Dismantling and erection of tower at Loc. No 332 of the 132KV Depota-Rowta line and associated works. |
11-03-2022 12:00 |
07-04-2022 12:00 |
08-04-2022 12:00 |
|
Tender Cancelled
|
37 |
|
Construction of approach road(to 132/33 KV Switchyard) at 132KV GSS,AEGCL,Dibrugarh |
08-03-2022 12:00 |
05-04-2022 14:00 |
05-04-2022 14:30 |
|
|
38 |
|
Repairing of water filtration tank at 132 KV Nalkata GSS, AEGCL,North Lakhimpur. |
09-03-2022 12:00 |
29-03-2022 14:00 |
30-03-2022 12:00 |
|
|
39 |
|
TENDER FOR ENGAGEMENT OF ACTUARY FOR VALUATION OF TERMINAL BENEFIT LIABILITIES OF ASEB EMPLOYEES PENSION FUND INVESTMENT TRUST |
10-03-2022 13:00 |
28-03-2022 12:00 |
28-03-2022 15:00 |
|
|
40 |
|
Repairing of Inspection Bungalow (IB) at 220KV Samaguri GSS, AEGCL. (Outside and inside room’s wall painting for beautification purpose) |
05-03-2022 12:00 |
26-03-2022 12:00 |
28-03-2022 13:00 |
|
|
41 |
|
Renovation of control room at 132 kV GSS, AEGCL,Dhemaji. |
04-03-2022 12:00 |
25-03-2022 14:00 |
28-03-2022 12:00 |
|
|
42 |
|
Expression of interest (EOI) for leasing of dark fibres of OPGW installed in AEGCL optical fibre network. |
16-02-2022 10:30 |
16-03-2022 17:00 |
17-03-2022 11:00 |
|
|
43 |
|
RENOVATION AND REPAIRING OF PROPOSED ACCOMMODATION OF
GM(CAZ), DGM CA T&C AND AGM T&C AND AGM COMM SAMAGURI AT
EXISTING LP SCHOOL BUILDING UNDER 220 KV SAMAGURI GSS
CAMPUS, AEGCL. |
01-03-2022 14:00 |
15-03-2022 14:00 |
16-03-2022 15:00 |
|
|
44 |
|
1. Construction of a New Parking shed for office of GM(CAZ), DGM CA T&C AND
AGM T&C AND AGM COMM Samaguri at existing LP School Building Under
220kV Samaguri GSS Campus, AEGCL.
2. Construction of new fencing for office of GM(CAZ), DGM CA T&C AND AGM
T&C AND AGM COMM Samaguri at existing LP School Building Under 220kV
Samaguri GSS Campus, AEGCL.
3. Construction of a new gate for the office of GM(CAZ), DGM CA T&C AND AGM
T&C AND AGM COMM Samaguri at existing LP School Building Under 220kV
Samaguri GSS Campus, AEGCL.
4. Construction of internal road for office of GM(CAZ), DGM CA T&C AND AGM
T&C AND AGM COMM Samaguri at existing LP School Building Under 220kV
Samaguri GSS Campus, AEGCL. |
01-03-2022 14:00 |
15-03-2022 12:00 |
16-03-2022 15:00 |
|
|
45 |
|
Supply, installation, Testing & Commissioning of SAMAST
COMPLIANT 0.2S CLASS ABT Meters and 05.S CLASS LT Meters at various Grid Substation of Assam Electricity Grid corporation Ltd. |
02-02-2022 14:00 |
10-03-2022 17:00 |
11-03-2022 14:00 |
|
|
46 |
|
Augmentation of 33kV Bus-II at Nazira GSS |
18-02-2022 12:00 |
10-03-2022 12:00 |
10-03-2022 14:30 |
|
|
47 |
|
Augmentation of 33kV Bus-III at Nazira GSS |
18-02-2022 12:00 |
10-03-2022 12:00 |
10-03-2022 14:30 |
|
|
48 |
|
Earth filling, dismantling of existing security fencing and
replace it with a new retaining wall for newly proposed 33 KV Lower Kopili Bay
at 132 KV Umrangso GSS, AEGCL. |
07-02-2022 12:00 |
07-03-2022 12:00 |
08-03-2022 12:00 |
|
|
49 |
|
Procurement of C category materials in all substations under Mirza T&T Circle. |
11-02-2022 12:00 |
04-03-2022 12:00 |
04-03-2022 13:00 |
|
|
50 |
|
Renovation & Repairing works of Control/ SAS room at 220kv
Samaguri GSS, AEGCL |
09-02-2022 12:00 |
02-03-2022 12:00 |
03-03-2022 13:00 |
|
|